TSMC's Arizona campus shows what a Brazos County plant could grow into
The Daily College Station team
Wondering what a chip plant needs from local water lines and power grids? KBTX looked at TSMC's campus in north Phoenix, which began as a single-fab project with a similar scope to the Brazos County plan. It's now expected to include at least a dozen facilities. The Dallas News says Brazos County has joined the race for a $23 billion facility.
Arizona's planned TSMC spending grew far past its $12 billion start
Source: KBTX News 3
View as table
| Value | |
|---|---|
| Arizona, 2020 plan | $12 billion |
| Arizona, Dec. 2022 | $40 billion |
| Arizona, now | $265 billion |
| Brazos County proposal | $22.6 billion |
Water is the big question. Citing Arizona's Family, KBTX reports the first fab alone uses about 5,300 acre-feet a year, roughly 1.7 billion gallons. That's enough to supply about 15,000 Phoenix households.
- Phoenix campus water use: 4.75 million gallons a day, mostly reclaimed
- Jobs: about 3,500 now, 6,000 expected for the first three fabs
- Federal aid: more than $10 billion under the CHIPS Act
- Brazos site: roughly 1.6 times the Arizona campus
TSMC's Arizona project grew from one fab to a dozen facilities
- 2020TSMC Arizona announced as a single-fab, $12 billion project.
- 2021TSMC first broke ground in Arizona.
- Dec. 2022Project expanded to include a second fab, at $40 billion.
- Late 2024The first Arizona fab began production.
- Jan. 2026Campus expanded to just over 2,000 acres.
Source: KBTX News 3
Sources: KBTX News 3, Dallas News