BusinessTop story
TSMC is eyeing a $22.6 billion chip plant south of College Station
The proposed TSMC site is about two thirds the size of Texas A&M's campus
Area of the proposed TSMC site, beside places you know
2,444 football fields would fit inside the proposed TSMC site
Source: KBTX News 3
View as table
| Area | |
|---|---|
| The proposed TSMC site | 3,232 acres (Proposed reinvestment zone) |
| Texas A&M's College Station campus | 5,200 acres |
| A football field | 1.3 acres (end zones included) |
If you've heard talk of a giant chip plant south of town, it's real, but it isn't a done deal. Taiwan Semiconductor Manufacturing Company (TSMC) has proposed a $22.6 billion facility on just over 3,200 acres in southern Brazos County. County officials confirmed Monday that the company is eyeing the area, and Arizona remains an alternative.
Tom Johnson of the Greater Brazos Partnership said the site could be the first of "five to six or more" fabs. He thinks Brazos County has "a good chance at landing this first fab," though TSMC is still weighing other states, mostly Arizona.
The proposal by the numbers
- $22.6 billion
- estimated investment
- 2,099
- direct jobs at most
- $133,000
- average salary
Source: KBTX News 3
- Site: north of Koppe Bridge Road, west of I&GN Road
- Land: under contract, but county records show it isn't purchased
- Buffer: TSMC wants to be 1,000 feet from homes
- Water: TSMC aims to reclaim more than 90%